A division of Russian engineer Rosatom has begun work on a 300MW wind farm within the Republic of Dagestan within the northern Caucasus.
The venture might be carried out in two phases, the primary of which includes the set up and commissioning of 61 generators with a capability of 152MW. This is because of be accomplished subsequent 12 months.
Fifty-nine items might be put in within the second part, and can start operations in 2026. When that occurs, the Novolakskaya wind farm will generate 879 GW/h of vitality a 12 months.
At current, 190 employees are current on the website within the Kumtorkalinsky, the place they’re putting in foundations and creating entry roads. A plant able to mixing 140 cubic metres of concrete an hour is working on the website.
Sergei Nazarov, the Russian Federation’s deputy minister for financial improvement, mentioned in a press assertion that the plant can be a “breakthrough” venture and would promote the “social and financial improvement of the North Caucasus Federal District”.
He mentioned: “I wish to notice that the wind farm will enable the creation of extra era within the Novolaksky District, offering a supply of environmentally pleasant vitality to stabilise the grid voltage, enhance robustness of energy provide to the inhabitants and supply the chance of financial and social improvement of the territory.”