The Toyota Stadium in Frisco, Texas, is about to get a $182 million renovation after the Frisco Metropolis Council on Sept. 17 accredited a public-private partnership with skilled soccer group FC Dallas.
Naples, Florida-based Manhattan Building Group will construct the mission, designed by Dallas-headquartered HKS Architects, in response to a information launch from FC Dallas. Manhattan can also be a part of the group that the College of South Florida tapped earlier this 12 months to construct its $340 million soccer stadium.
Positioned about 27 miles from downtown Dallas, Toyota Stadium is Main League Soccer’s third-oldest soccer-specific venue and has housed Frisco Unbiased Faculty District athletic occasions since 2005. The objective of the renovation is to modernize the power with a purpose to improve the visitor expertise, “as soon as once more establishing Toyota Stadium as one of many premier services in Main League Soccer,” FC Dallas Chairman and CEO Clark Hunt mentioned within the launch.
“When Toyota Stadium opened in 2005, it was a state-of-the-art facility that was forward of its time, and the stadium’s success has helped pave the best way for dozens of different soccer-specific stadiums throughout the nation,” Hunt mentioned.
Enhancements entail a brand new roof, 10% extra seating and 26% extra loos and state-of-the-art sound system and video boards, in response to FC Dallas. The improve contains two new suite ranges, extra concessions, three new golf equipment and up to date media services. It can additionally enhance accessibility and improve the sector drainage system for extra environment friendly water clearance.
In response to ABC 8, funding sources for the renovation are:
- 44% by Tax Increment Reinvestment Zone income.
- 36% by Hunt Sports activities Group, the proprietor of FC Dallas.
- 20% by the Frisco Group Growth Corp.
- Value overruns to be paid by Hunt Sports activities Group.
Building work is about to begin in 2025 and end within the first quarter of 2028. Video games and occasions will proceed whereas development is underway: Work is deliberate to start on the east facet of the stadium in Q1 of 2025, after which transfer to the west facet in the summertime of 2026 whereas the east facet reopens, in response to the FC Dallas web site.