Employees rigorously put in the final curtain wall programs and metallic panels on a state-of-the-art most cancers care facility in Towson, Maryland, simply exterior downtown Baltimore.
DPR, the overall contractor of the challenge, then rapidly pivoted to finish the outside facade in preparation for a ribbon-cutting ceremony going down throughout the location.
For months, DPR’s crew had coordinated between the 2 interconnected buildings — the $72 million Sandra R. Berman Pavilion and the $73 million Louis and Phyllis Friedman Constructing. Collectively, the buildings kind a part of the Promise Challenge, a major enlargement to the Higher Baltimore Medical Heart.
So, as native officers gathered in November 2023 to chop the ribbon in entrance of the finished Friedman Constructing, they weren’t simply celebrating the opening of a brand new inpatient facility. In addition they pointed to the Berman Pavilion — an early glimpse of a second transformative challenge coming to life.
Behind the brand new facade of the Berman Pavilion, development continued in full power.
Because the challenge continues to work towards its 2025 completion, DPR hosted Building Dive for a tour of the 2 websites, showcasing the behind-the-scenes efforts concerned in each buildings.
From demolition to development
The Berman Pavilion, a state-of-the-art most cancers care middle, will consolidate all outpatient most cancers providers at GBMC into one centralized location.
Building formally started in July 2022 with the demolition of the previous Superior Radiology constructing, clearing the way in which for the pavilion. As DPR started laying the inspiration, work additionally continued on the adjoining Friedman Constructing.
Administration on these simultaneous tasks required cautious coordination to make sure zero disruption to hospital operations, mentioned Ariel Rodriguez, DPR challenge supervisor. For instance, the DPR crew made positive the GBMC ambulance route, entrance to the hospital and parking for sufferers, guests and workers all remained accessible in the course of the construct.
By early 2023, progress accelerated on the pavilion challenge, with the set up of a tower crane in March signaling the beginning of vertical development. The post-tension concrete construction continued to take form over the next months, resulting in a challenge milestone in August 2023 when the pavilion was topped out, in accordance with DPR.
In October 2023, DPR put in curtainwall programs and metallic panels on the outside, with ending touches on the facade persevering with into December. As the outside of the pavilion neared completion, DPR shifted its consideration to the inside.
The challenges of managing two main development tasks concurrently on an energetic hospital campus remained vital, mentioned Zach Root, DPR senior challenge supervisor. For instance, the tight website required shared sources between the 2 tasks, corresponding to a standard trailer advanced and materials laydown areas, in accordance with DPR.
The 76,340-square-foot facility will home quite a lot of specialties, together with genetics, infusion remedy, gynecologic and medical oncology and oncology assist providers. The constructing sits atop a newly constructed four-story parking storage.
DPR expects to complete the Berman Pavilion in early 2025, in accordance with the development agency.
Completion of the Friedman Constructing
The three-story, $73 million inpatient facility options 60 state-of-the-art affected person rooms. The constructing additionally serves as GBMC’s new principal entrance, welcoming sufferers and guests right into a light-filled atrium.
Prefabrication performed a key position throughout development of the Friedman Constructing, in accordance with DPR. The offsite work not solely sped up development, but additionally helped preserve security and effectivity on the busy hospital campus.
For instance, DPR constructed nurse stations and reception desks for the atrium at an offsite store. These sections had been then rigorously examined to make sure alignment, significantly the curved components, earlier than being delivered to the hospital for set up.
Equally, DPR constructed about 60 prefabricated headwalls offsite whereas different development actions progressed on the Friedman Constructing. DPR’s self-perform crew put in these headwalls, important for the affected person rooms, in levels. The prefab of the headwalls considerably lowered development time, congestion and security dangers on the energetic hospital website, mentioned Rodriguez.
To additional cut back the affect on the hospital, work was usually sequenced for off-hours, in accordance with DPR.
DPR additionally briefly relocated the chapel and medical library to different areas of the hospital throughout development. That included the preservation of the stained-glass home windows within the current chapel.
To do that, DPR labored carefully with the GBMC’s chaplain and with its commerce companion, Harrisonburg, Virginia-based Glass and Metals, to rigorously doc and deconstruct the home windows for storage in a temperature-controlled warehouse. As soon as development of the brand new chapel was underway, DPR reinstalled the stained glass in custom-built frames.
The Friedman Constructing opened in November 2023, and is presently absolutely operational.