Prolongation Cost Calculator
This prolongation cost calculator multiplies weekly time-related site preliminaries by compensable weeks and optionally adds a head-office overhead percentage. It is a general estimating and scenario tool, not legal advice, a claims valuation or a finding that any delay is compensable.
By Dr. Hassan Khames EliwaLast updated
Result
- Time-related site cost
- $20,000.00
- Head-office overhead addition
- $2,000.00
How it works
Build a defensible weekly allowance
Start with the site costs that genuinely continue with time: for example, an agreed site management allowance, accommodation hire and appropriate temporary services. Do not put every project cost into the weekly figure simply because the project finishes late. One-off mobilisation, production-related resources and costs already recovered elsewhere require separate consideration. Keep the supporting build-up alongside the estimate so reviewers can see what is included.
Multiply by the relevant period
Time-related site cost equals weekly preliminaries multiplied by compensable weeks. Fractional weeks are allowed, which is useful when a scenario uses part of a week. The calculator does not identify the delay period, analyse the critical path or separate overlapping causes. You supply the weeks after whatever programme and entitlement assessment is appropriate for the exercise.
The optional head-office addition equals site cost multiplied by the entered overhead percentage. Total indicative cost is the sum of site cost and that addition. Enter zero to leave head-office overhead out. This simple percentage is not a recognised entitlement formula by itself and does not model actual unabsorbed overhead, lost opportunity or profit. Keep profit and other heads of cost outside this calculation unless separately supported and intentionally included in your underlying allowance.
Use it as a scenario, not a claim conclusion
The Society of Construction Law Delay and Disruption Protocol discusses the importance of records and the distinction between delay and monetary compensation. Its guidance does not replace the contract or applicable law. The calculator cannot resolve concurrency, notice compliance, causation, mitigation, disruption or the appropriate measure of loss.
For planning, compare a base scenario with a shorter mitigated period, but retain the operational assumptions behind both. The activity duration calculator can support resource-duration checks; it does not prove compensability either. Present the output as an indicative allowance with exclusions, rather than attaching unwarranted certainty to a neatly formatted total.
Worked example
Example: default planning allowance
Weekly time-related preliminaries of $5,000 over 4 compensable weeks give $20,000 in site cost. A 10% head-office addition is $2,000. The indicative total is $22,000. These inputs illustrate the arithmetic only; the addition is not automatically recoverable because it appears in the calculation.
Example: fractional period without head-office overhead
With weekly preliminaries of $7,200 and 2.5 compensable weeks, site cost is $18,000. Entering 0% head-office overhead gives an addition of $0 and an indicative total of $18,000. The fractional week is multiplied directly, without rounding the duration to a complete week.
Expert tips
Common mistakes
- Equating all delay weeks with compensable weeks. Time entitlement and money entitlement are distinct questions, and the calculator deliberately leaves that assessment to the user.
- Applying an overhead percentage as if it proves actual loss. A percentage can be a budgeting convention, but it does not establish causation, entitlement or evidential sufficiency.
- Ignoring avoided costs or mitigation when preparing a scenario. A time extension can change the pattern of expenditure rather than simply repeat the original weekly total.
Frequently asked questions
Does this prove a claim?
No. The result is a multiplication-based estimate. A claim requires the relevant contractual and legal basis, evidence of causation and loss, and compliance with any applicable procedural requirements.
Can I enter part of a week?
Yes. Fractional weeks are supported and multiplied directly by the weekly allowance. Make sure the fraction represents a consistent period rather than mixing calendar days and working-day rates.
What belongs in weekly preliminaries?
Include the time-related site costs within your stated scope. Review supervision, accommodation and hire individually, excluding items that do not continue or are already accounted for elsewhere.
Is overhead the same as profit?
No. Head-office overhead is a business cost allocation, while profit is a return above cost. This calculator adds only the stated overhead percentage and has no separate profit field.
Which overhead formula does it use?
It uses a simple percentage of the calculated site prolongation cost. It does not implement Hudson, Emden, Eichleay or any other claims formula, and should not be described as doing so.
Are disruption costs included?
Not separately. Loss of productivity, acceleration and disruption can involve different evidence and valuation methods. Keep those assessments distinct rather than burying them inside a weekly allowance without explanation.
Related calculators
Related guides
Construction & ProjectProlongation Costs and Time-Related OverheadsBuild a transparent time-related overhead estimate, separate one-off costs, and avoid double counting in a worked duration example.17 November 2026 · 7 min read
Construction & ProjectLiquidated damages for construction delayUnderstand delay triggers, calendars, caps and assessment records without confusing calculator arithmetic with legal entitlement.15 November 2026 · 8 min read
Construction & ProjectActivity duration from production ratesConvert quantities, crew outputs and working hours into defensible activity durations without double-counting productivity allowances.14 November 2026 · 8 min readSources and standards
About the author
Dr. Hassan Khames Eliwa holds a PhD in Construction & Built Environment and has more than 20 years of international project controls experience. He is Director of Eliwa Project Controls Limited in Auckland and founder of PMMilestone.org and PMMilestone.com.
Buy me a coffee