Excavation Calculator
This excavation calculator separates earthwork into bank volume before digging, loose volume after excavation, and compacted yield after placement. Enter rectangular dimensions, a swell percentage and a separate shrink percentage to estimate the three quantities without mixing their reference states.
By Dr. Hassan Khames EliwaLast updated
Result
- Bank excavation
- 150.00 m³
- Compacted yield
- 135.00 m³
How it works
Start with the undisturbed ground
Bank volume equals length × width × average depth. Metric dimensions are metres and return cubic metres. Imperial dimensions are feet; their product is divided by 27 to return cubic yards. Measure the excavation envelope, not just the finished concrete footprint. Working room, permitted side slopes and formation levels can change the quantity substantially. The simple rectangle is a quantity model, not an excavation design.
Swell and shrink have different jobs
Swell, sometimes called bulking, describes the increase from bank material to loose excavated material. Loose haul volume = bank volume × (1 + swell ÷ 100). A 25% swell means one bank cubic metre becomes 1.25 loose cubic metres. That is the quantity relevant to a volume-limited truck body, before allowing for safe loading or spillage.
Shrink here means the reduction from bank volume to the final compacted volume: compacted yield = bank volume × (1 − shrink ÷ 100). A 10% shrink means one bank cubic metre produces 0.90 compacted cubic metres. It is not a percentage removed from the loose volume. Applying both percentages successively would answer a different question and understate the yield used here.
Match the factor to the material
Use project earthwork information, trial compaction results or a documented local material assessment. The calculator deliberately supplies no soil-class factor table. Rock fragmentation, moisture, organic content and placement specification can change the relationship. Separate unsuitable spoil from reusable material before relying on the compacted yield. Values above zero and up to 100,000 are accepted for dimensions; swell is limited to 200%, and shrink must remain below 100%.
Worked example
Scenario 1: a small service excavation
An excavation 20 m long, 5 m wide and 1.5 m deep contains 150.00 m³ in the bank. At 25% swell, loose haul volume is 187.50 m³. At 10% shrink referenced to bank volume, compacted yield is 135.00 m³. The two factors describe separate destinations for the same original material; adding those volumes would double-count it.
Scenario 2: an imperial foundation cut
A rectangular cut measuring 60 ft × 12 ft × 3 ft contains 2,160 cubic feet, or 80.00 yd³ bank volume. With 20% swell, loose haul volume becomes 96.00 yd³. A separate 15% bank-to-compacted shrink gives 68.00 yd³ compacted yield. These are volume estimates, not truck counts: a truck can reach its legal mass limit before its body is full.
Carry the estimate into the takeoff
Label each subtotal BCY, LCY or CCY when the job uses cubic yards, and spell out the reference state on metric schedules. If part of the cut is stockpiled and part leaves site, split the bank quantity first. Apply the relevant material factors to each stream rather than multiplying a mixed spoil total by a convenient average.
Expert tips
Common mistakes
- Using structural dimensions as digging dimensions. Blinding, access and temporary works can require a larger excavation. Include only approved allowances; this tool does not tell you what side slope or support arrangement is safe.
- Calling swell a waste allowance. Bulking changes occupied volume without creating more soil solids. Waste, contamination removal and imported replacement are separate quantity decisions that need their own lines in the estimate.
- Ordering transport from volume alone. Check material density, moisture, axle limits and route restrictions with the haulier. A volume estimate cannot certify a legal payload or predict the number of achievable trips in a shift.
Frequently asked questions
Are swell and bulking the same here?
Yes. Both refer to the increase from undisturbed bank volume to loose excavated volume. They do not refer to added material or to the final compacted condition.
Is shrink applied after swell?
No. Both outputs start independently from bank volume. To compare loose and compacted quantities, use their separate factors rather than subtracting the shrink percentage from the swollen volume.
Can I estimate a trench with sloping sides?
Use an independently calculated equivalent average width only when that represents the actual geometry. For variable sections, calculate segments separately. The calculator does not design trench slopes, shielding or shoring.
Can compacted yield exceed bank volume?
Not with this shrink-only model. A material relationship that produces expansion after placement needs a separately documented conversion rather than a negative shrink entry.
Does the estimate include excavation safety requirements?
No. Protective systems, access, utility location, water control and competent-person inspections remain separate requirements. Consult applicable excavation rules before work begins, regardless of the quantity shown.
Related calculators
Related guides
Construction & ProjectHow to order concrete without running short or overpayingA field-focused guide to concrete quantities, thickness checks, sensible allowances and the delivery details that prevent expensive surprises.14 November 2026 · 7 min read
Construction & ProjectThree-point estimating: when PERT beats a single guessA practical guide to three-point duration estimates, weighted averages and the limits of turning uncertain activities into a promised date.14 November 2026 · 7 min readSources and standards
About the author
Dr. Hassan Khames Eliwa holds a PhD in Construction & Built Environment and has more than 20 years of international project controls experience. He is Director of Eliwa Project Controls Limited in Auckland and founder of PMMilestone.org and PMMilestone.com.
Buy me a coffee